Project Profile

Central Mid Level and High Level Areas Water Supply

Name
Improvement to Hong Kong Central Mid Level and High Level Areas Water Supply
Commencement
08/2008
Completion
09/2012
Client
Water Supplies Department
Consultant
AECOM
Main Contractor
EXCEL Engineering Co. Ltd.
Scope of  Work
E&M Design, Supply, Installation, Testing & Commissioning of Pumping Stations
Description
Provision of more service reservoirs to increase fresh water supply for Central Mid-level and High Level Areas including Existing Western Fresh Water & Salt Water Pumping Station, Existing and New Kotewell Road Fresh Water Pumping Station, New Hatton Road Fresh Water Service Reservoir, Existing and New Peak Fresh Water Pumping Station
Nature of Work
Engineering & Procurement Contract
Main Equipment
Centrifugal Pumps
Main Process
Fresh Water and Salt Water Pumping System
Capacity
350 m3/d - 24,000 m3/d