Project Profile

Yung Shue Wan Sewage Treatment Works

Name
Yung Shue Wan Sewage Treatment Works
Commencement
05/2010
Completion
01/2014
Location
Yung Shue, Lamma Island
Client
Drainage Services Department
Consultant
Scott Wilson CDM Joint Venture
Main Contractor
Leader Civil Engineering Corporation Ltd.
Scope of  Work
Process and E&M Design, Supply, Installation, Testing & Commissioning of the Sewage Treatment Works
Description
Construction of the new sewage treatment works by using Membrane Bioreactor (MBR) technology at Yung Shue Wan, Lamma Island
Nature of Work
Design & Build Contract
Main Equipment
Submerged Flat Sheet Membrane Modules
Main Process
Coarse Screens, Pumping Station, Fine Screens, Grit Removal, Grease Separation, Anoxic Denitrification, Membrane Bioreactor, Sludge Dewatering, Deodorization
Capacity
8550 m3/d