Project Profile

Sok Kwu Wan Sewage Treatment Works

Name
Sok Kwu Wan Sewage Treatment Works
Commencement
05/2010
Completion
02/2014
Client
Drainage Services Department
Consultant
Scott Wilson CDM JV
Main Contractor
Leader Civil Engineering Corporation Ltd.
Scope of  Work
Process and E&M Design, Supply, Installation, Testing & Commissioning of the Sewage Treatment Works
Description
Construction of the new sewage treatment works by using Membrane Bioreactor (MBR) technology at Sok Kwu Wan, Lamma Island
Nature of Work
Design & Build Contract
Main Equipment
Submerged Flat Sheet Membrane Modules
Main Process
Pumping Stations, Fine Screens, Grit Removal, Grease Separation, Anoxic Denitrification, Membrane Bioreactor, Sludge Dewatering, Deodorization
Capacity
4290 m3/d