Project Profile

Shanghai Bailonggang WWTP

Name
Shanghai Bailonggang Wastewater Treatment Plant
Commencement
10/2011
Completion
12/2012
Client
Shanghai Bailonggang Wastewater Treatment Company
Consultant
Shanghai Municipal Engineering Design and Research Institute
Scope of  Work
E&M Design, Supply, Installation, Testing & Commissioning of the Treatment Systems
Description
The project involved the construction of the Anaerobic-Anoxic-Oxidation System, Deodorization System as well as the Effluent Pumping Station of the Sewage Treatment Plant
Nature of Work
Engineering & Procurement Contract
Main Equipment
Equipment in Biological Reactor, Odor System and Effluent Pumping Station
Main Process
A2O Process
Capacity
2,800,000m³/day