Project Profile

Tianjin Dongjiao STW

Name
Tianjin Dongjiao Sewage Treatment Works
Commencement
03/2010
Completion
10/2010
Client
Tianjin Machinery and Electric Equipment I& E Co., Ltd.
Consultant
North China Municipal Engineering Design & Research Institute
Scope of  Work
Design, Supply, Installation Supervision, Testing & Commissioning of the System
Description
"The project involve the construction of the Gas Holder System of the Wastewater Treatment Plant "
Nature of Work
Engineering & Procurement Contract
Main Equipment
SATTLER Gas Holder System
Capacity
2 X 5,000m3